20040,5934 <br />9.8 Overtime and Additional Shifts: If ordered by SIGNATURE in writing, Trade Contractor shall work <br />overtime and/or add additional manpower or shifts: <br />(a) If Trade Contractor is not behind schedule, SIGNATURE will pay Trade Contractor the actual <br />additional premium portion of wages for overtime or additional shift work not then included in the <br />Trade Contract Price, plus any taxes on such additional wages and reasonable overhead and profit. <br />Contract price shall be adjusted by change order as set forth in section 12 for all additional <br />charges. <br />(b) If Trade Contractor, through its own sole or partial fault or neglect, is behind schedule, <br />SIGNATURE may order Trade Contractor to increase its manpower or to work, at Trade <br />Contractor's expense, any overtime or additional shifts or take any other action necessary to <br />expedite the Work to meet the Project Schedule. <br />SECTION 10 <br />Delays and Extensions of Time <br />10.1 Delays Caused by Others: SIGNATURE shall not be liable to Trade Contractor for any delay, disruption <br />or interference to Trade Contractor's Work caused by the act, omission, neglect or default of the Owner or <br />the Architect or their respective contractors, subcontractors, employees, servants, agents or consultants, or <br />by reason of fire or other casualty, or on account of riots or of strikes, or other combined action of the <br />workmen or others, or on account of any acts of God, or any other cause beyond SIGNATURE's direct <br />control; provided, however, SIGNATURE will cooperate with Trade Contractor in submitting against the <br />Owner or Architect, any just claim arising therefrom which is permitted by the Contract Documents and <br />applicable law. Trade Contractor shall reimburse SIGNATURE for all reasonable expenses incurred by <br />SIGNATURE in submitting any such claims on behalf of Trade Contractor. Trade Contractor shall not <br />claim any time extension, cost reimbursement, compensation or damages for any delay, disruption or <br />interference to the Work except to the extent that SIGNATURE is entitled to corresponding time extension, <br />cost reimbursement, compensation or damages from the Owner or Architect under the Contract Documents <br />and applicable law. Trade Contractor's recovery shall be limited to the amount, if any, which <br />SIGNATURE recovers, on behalf of Trade Contractor with respect to such claim. Payment by the Owner <br />or other liable person or entity shall be by an express condition precedent to SIGNATURE's duty of <br />payment to Trade Contractor. <br />10.2 Delays Caused Solely by SIGNATURE: Should Trade Contractor's Work be delayed, disrupted or <br />interfered with solely as a result of wrongful acts or omissions of SIGNATURE or any person or entity for <br />whom SIGNATURE is liable, then, at SIGNATURE's sole option, Trade Contractor shall receive either: <br />(a) an extension of time equal to the actual impact of the delay, disruption or interference on the <br />critical path of Trade Contractor's Work, or <br />(b) additional compensation as provided in Section 9.8 (a), but only if a written claim for delay is <br />submitted to SIGNATURE within forty-eight (48) hours from the time of the commencement of <br />such delay, disruption or interference. <br />Failure to provide such written claim within the prescribed time period shall result in an irrevocable waiver <br />of any such claim. The extension of time or the additional compensation provided pursuant to this Section <br />10.2 shall be Trade Contractor's sole and exclusive remedy against SIGNATURE for delays, disruptions or <br />interference's caused by the acts or omissions of SIGNATURE or any person or entity for whom <br />SIGNATURE is liable, and Trade Contractor shall have no right or entitlement to additional compensation, <br />whether direct or indirect, for such delays, disruptions or interference's. Trade Contractor expressly <br />waives any claim against SIGNATURE for damage for delay, acceleration, interference, extra work <br />resulting from such delay, extended overhead, wage escalation, overtime wage provisions, lost opportunity, <br />or lost profit or financial impact on Trade Contractor's other projects. SIGNATURE's exercise of its rights <br />pursuant to Section 9.6 shall not constitute a delay, disruption or interference with Trade Contractor's <br />Work under this Section 10.2. <br />Initial 4rM / <br />11 <br />