200405934 t. <br />SECTION 9 <br />Schedule and Coordination <br />9.1 Time of the Essence: SIGNATURE and/or the Owner may sustain severe financial loss if the Project or <br />any part of it is delayed because Trade Contractor fails to perform any or all of its Work in accordance with <br />this Trade Contract, the Contract Documents or the Project Schedule and changed as prepared by the onsite <br />superintendent or project manager. <br />9.2 Commencement of Trade Contractor's Work: Trade Contractor shall commence its Work when <br />directed by SIGNATURE to do so and shall diligently and continuously perform and complete its Work so <br />that neither SIGNATURE nor any other person or entity will be delayed in completing its work on the <br />Project by any act or omission of Trade Contractor. If, for any reason, Trade Contractor's Work is ordered <br />stopped, Trade Contractor shall resume its Work within the time stated in a written notice from <br />SIGNATURE. <br />9.3 Coordination: Trade Contractor shall coordinate its operations with all other contractors, subcontractors <br />and trades working on the Project. Should the proper and accurate performance of the Trade Contractor's <br />Work depend upon the proper and accurate performance of the work of other contractors, Trade Contractor <br />shall carefully examine such other work, determine whether it is in fit, ready and suitable condition for the <br />proper and accurate performance of the Work hereunder, and before proceeding with its Work, report <br />promptly, in writing, any such improper conditions and defects to SIGNATURE and allow SIGNATURE a <br />reasonable time to have such improper conditions and defects remedied. Failure by Trade Contractor to <br />report any such defective or uncompleted work by others shall constitute a waiver and estoppel of any <br />claim by Trade Contractor for any damage or for any claim for an extension of time arising out of such <br />defective or uncompleted work. Further, Trade Contractor shall be liable to SIGNATURE for any damage <br />caused SIGNATURE by Trade Contractor's failure to report any such defective or uncompleted work by <br />others. <br />9.4 Shop Drawings and Other Submissions Required by the Contract Documents: Trade Contractor shall <br />submit all shop drawings, samples and other required submittals in strict accordance with this Trade <br />Contract, the Contract Documents and SIGNATURE's schedule requirements so that Trade Contractor <br />does not delay its own Work, the work of SIGNATURE or any other person or entity. <br />9.5 Trade Contractor's Conformance to Project Schedule: Trade Contractor shall continuously monitor the <br />Project Schedule so as to be fully familiar with the timing, phasing and sequence of operations of its Work <br />and of other work on the Project, and shall execute the Work in accordance with the requirements of the <br />Project Schedule, including any revisions thereto and shall meet all interim or final milestone dates <br />included in the Project Schedule. Trade Contractor's Superintendent or other authorized representative <br />shall be required to attend a weekly on site Trade Contractor's Scheduling Meeting. This meeting shall be <br />held at the job trailer each Monday at 8 AM. Signature shall have the right to backcharge (as described in <br />section 5.6) Trade Contractor $500 for each meeting their representative fails to attend without prior <br />written consent of Signature's Project Superintendent. <br />9.6 Priority of Work: Throughout the course of the Project, SIGNATURE shall have the right to modify the <br />Project Schedule, to suspend, delay, or accelerate, in whole or in part, the commencement or execution of <br />Trade Contractor's Work or any portion thereof or to vary the sequence thereof, to reasonably decide the <br />time, order and priority of the various portions of Trade Contractor's Work, and all other matters relating to <br />the scheduling and coordination of Trade Contractor's Work with other work on the Project in order to <br />respond to job conditions and/or achieve timely completion of the entire Project. Trade Contractor shall <br />not be entitled to any additional compensation for decisions or changes made by SIGNATURE pursuant to <br />this Section 9.6 except as provided in Section 9.8. <br />9.7 Punch Out: Trade Contractor shall be responsible for a minimum of two building punch lists the first shall <br />be prepared by the on -site superintendent prior to the Owner's inspection. The second shall be prepared by <br />the Owner or their agent and be based on their building inspection. In both instances Trade Contractor shall <br />have four (4) days from the date of the punch list to complete their work. If Trade Contractor fails to <br />comply with this schedule SIGNATURE may contract with others without notice to complete for the costs <br />thereof, plus ten percent (10 %) for overhead and ten percent (10 %) for profit. SIGNATURE shall also have <br />the right to complete the work on behalf of the Trade Contractor with SIGNATURE employees and <br />backcharge Trade Contractor $75.00 per man-hour for each hour spent completing the work. <br />Initial <br />10 <br />