HALL COUNTY HIGHWAY DEPARTMENT Change Order No: 001 <br /> IContract Change Order Date: 10/2/2018 <br /> County Project Number: 2018-2019 Asphaltic Concrete Resurfacing, Phase 1 (Fall 2018) <br /> Change Order Description: To Extend the Completion Date 2 weeks and <br /> Change the Mix Type for the Hillside Drive resurfacing in Cairo <br /> Contractor: J.I.L.Asphalt Paving Co. <br /> One R Rd east of NE Hwy 11 <br /> Hillside Dr east of NE Hwy 11 <br /> Wood River Rd west of NE Hwy 11 <br /> Project Locations: Holling Drive west of Alda Link L40C Letting Date: August 21,2018 <br /> Contract Award Date: September 4,2018 <br /> Contract Amount before Change Order $1,029,198.60 <br /> Original Revised Change <br /> Item Unit of Contract Contract Bid Order Amount of Change <br /> # Item Description Measure Quantity Change Quantity Price Price <br /> Hillside Drive in Cairo east of NE Hwy 11 <br /> 3 Asphaltic Concrete,Type"LC"at 1" Tons 400 -400 0 $ 100.25 N.A. $ (40,100.00) <br /> thick (AC PG 64-22 is subsidiary) <br /> 3a Asphaltic Concrete,Type"SPR-Fine at Tons 0 400 400 N.A. $76.00 $ 30,400.00 <br /> 1"thick (AC PG 64-22 is subsidiary) <br /> Asphaltic Concrete for Driveways <br /> 4 Type"LC" Tons 11 -11 0 $ 110.25 N.A. $ (1,212.75) <br /> (Asphalt Binder is subsidiary) <br /> Asphaltic Concrete for Driveways <br /> 4a Type"SPR-Fine" Tons 0 11 11 N.A. $86.00 $ 946.00 <br /> (Asphalt Binder is subsidiary) <br /> Total for Change Order: I $ (9,966.75) <br /> Revised Contract Amount after Change Order: ( $ 1,019,231.85 <br /> Change Order Narrative <br /> The bid's for the fall resurfacing were opened on August 21, 2018. Since the bid award was made 2 weeks later on <br /> September 4, 2018,hte completion dates should be pushed back 2 weeks later. The substantial completion date is <br /> being moved from October 12, 2018 to October 26,2018.The final completion date is being moved back from October <br /> 26,2018 to November 9, 2018. <br /> The mix type for Hillside Drive is being changed from "LC"to"SPR-Fine"to result in an estimated cost savings of almost <br /> $10,000.The"SPR-Flne"mix is a good mix and has performed successfully on a number of non-county projects. <br /> / �. October 2, 2018 <br /> z Jane Ri hardson Date <br /> 1 tI Count :oard hair <br /> E. /'d A. i October 2, 2018 <br /> Jer. Atkins,President Date <br /> . .Asphalt Paving Co. <br />