6. 9:30 AM --- BID OPENING FOR MATERIALS FOR BRIDGE PROJECT C40(378) ON 60TH <br /> ROAD NORTH OF BARROWS ROAD <br /> The following bids were received. <br /> BIDDER BID SECTION A TOTAL BID SECTIONS B & C <br /> Husker Steel <br /> Columbus, NE <br /> Bid Bond enclosed $30,850.00 $51,481.80 <br /> Midwest Sales & Service <br /> Schuyler, NE <br /> Bid Bond enclosed $33,199.46 $26,702.09 <br /> Quandt made a motion and Lanfear seconded to accept the bids and refer them to the public <br /> works committee and come back with a recommendation today. Arnold, Bredthauer, Lancaster, <br /> Lanfear, Quandt, Richardson and Schuppan all voted yes and none voted no. Motion carried. <br /> 11 C)SET THE BID OPENING FOR THE RENOVATION OF THE EXTERIOR STEPS AT THE <br /> HALL COUNTY COURTHOUSE FOR OCTOBER 31, 2017 AT 9:45 A.M. BIDS DUE BY <br /> OCTOBER 30, 2017 BY 5:00 P.M. - Mr. Humphrey provided a copy of the specifications. <br /> Discussion was held and noted that he included washing the whole building to clean it up and <br /> then it would all match. <br /> Bredthauer noted that because the fact that it is a historical building it should all be the same. <br /> and it would be better if it is done this way. They would also put a sealer on the brick to help <br /> keep it clean. It is historically good to preserve it. It is up to the board the scaffolding would be <br /> in place so it could all be done. The cost to do it all would be about $100,000.00 just to do the <br /> steps would be half of that number. <br /> Quandt stated it would be better to have the information ahead of time. <br /> Richardson stated it makes sense to the rest of the building it seems whatever is selected is <br /> wrong. <br /> Mr. Zitterkopf suggested bidding it separately. <br /> Schuppan stated the board can reject all bids or make an alternate and price it separately. It <br /> would be good to do it at the same time and not have to set up twice. They will bring this back <br /> in 2 weeks. <br /> 11 D) DISCUSSION ON THE INSTALLATION OF A WATER COOLER FOR VETERANS <br /> SERVICE OFFICE - Mr. Humphrey provided a copy of the estimate for a water cooler for the <br /> labor material and equipment. He stated that there was a water cooler there when they moved <br /> into the building but they asked to have it removed. He is proposing to put it in the same place <br /> but they would have to move an ADA button. They did discuss a cheaper system or renting a <br /> system from Culligan with the hot and cold water. They would have to buy the bottles at $8.00 <br /> apiece and there would be a delivery charge of$4.00. He noted that each department is to pay <br /> for this. <br /> Schuppan stated that his daughter installed one of these and question if there are other <br /> alternative systems out there. <br /> 3 <br />